Fall Build Schedule

Volunteer activities-in blue: work usually completed on Saturdays of that week, with exception of Nampa School District students who will build during the week. (No construction experience needed.) Committed groups in red

Bring: Water bottle! Hammer and work gloves, if applicable, Dress for the weather with layered clothing, hat, sunscreen.  No shorts or sandals!

Time: 9:00 AM until 4-5 PM    Stay for a partial or full day. We provide lunch.

Location: Lot to be determined, somewhere in Nampa

Week of:

August 15 Excavation

August 22 Footings and foundation

August 29 Any additional Sub work. Nampa School district students may begin working.

Sept. 06  Pony walls and install decking Sept. 10 Lunch:

Sept. 12  Framing Sept. 17 Lunch:

Sept. 19  Framing and begin interior walls Sept. 24 Lunch:

Sept. 26  Interior walls Oct. 01 Lunch:

Oct. 03  Begin building/setting roof trusses Oct. 08 Lunch:

Oct. 10  Finish roof tresses and interior walls Oct. 15 Lunch:

Oct. 17  Roof decking and sheath exterior Oct. 22 Lunch:

Oct. 24 Roof and exterior work Oct. 29 Lunch:

Oct. 31  Install windows and ‘dry-in” house  Nov. 05 Lunch:

Subs rough-in plumbing, electrical, HVAC

Nov. 07  Continue roofing begin installing vinyl siding Nov. 12 Lunch:

Nov. 14  Continue working on exterior until finished Nov. 19 Lunch:

Thanksgiving week

Nov. 28  Begin insulating interior Dec. 03 Lunch:

Dec. 05 Insulate and begin hanging sheetrock Dec. 10 Lunch:

Dec. 12 Sheetrock

Dec. 19 Finish hanging sheetrock

Christmas week

New Years week

Jan. 02  Begin taping sheetrock Jan. 07 Lunch:

Jan. 09  Taping and texturing Jan. 14 Lunch:

Jan. 16  Taping and texturing Jan. 21 Lunch:

Jan. 23  Prime interior Jan. 28 Lunch:

Jan. 30  Finish priming all interior walls Feb. 04 Lunch:

Feb. 06  Begin interior painting Feb. 11 Lunch:

Feb. 13  Finish interior painting Feb. 18 Lunch:

Feb. 20  Hang doors Lunch: Sub to install interior trim and cabinets, hang doors

Feb. 27  Begin installing interior trim

March 05  Finish all doors and trim Lunch:

March 12  Caulking March 17 Lunch:

March 19  Caulking and clean interior March 24 Lunch:

Spring break

April 02  Install cabinets Lunch:

April 09  Fence building April 14 Lunch: Sub to install floor coverings

April 16  Landscaping and fence building complete April 21

April 23  Misc. work completed

April 30  Clean up Subs to finish

May 07 Final inspection

May 14 House Dedication

To schedule your “build day,” or for more information call 459-3344, or Contact Us