Volunteer activities-in blue: work usually completed on Saturdays of that week, with exception of Nampa School District students who will build during the week. (No construction experience needed.) Committed groups in red
Bring: Water bottle! Hammer and work gloves, if applicable, Dress for the weather with layered clothing, hat, sunscreen. No shorts or sandals!
Time: 9:00 AM until 4-5 PM Stay for a partial or full day. We provide lunch.
Location: Lot to be determined, somewhere in Nampa
Week of:
August 15 Excavation
August 22 Footings and foundation
August 29 Any additional Sub work. Nampa School district students may begin working.
Sept. 06 Pony walls and install decking Sept. 10 Lunch:
Sept. 12 Framing Sept. 17 Lunch:
Sept. 19 Framing and begin interior walls Sept. 24 Lunch:
Sept. 26 Interior walls Oct. 01 Lunch:
Oct. 03 Begin building/setting roof trusses Oct. 08 Lunch:
Oct. 10 Finish roof tresses and interior walls Oct. 15 Lunch:
Oct. 17 Roof decking and sheath exterior Oct. 22 Lunch:
Oct. 24 Roof and exterior work Oct. 29 Lunch:
Oct. 31 Install windows and ‘dry-in” house Nov. 05 Lunch:
Subs rough-in plumbing, electrical, HVAC
Nov. 07 Continue roofing begin installing vinyl siding Nov. 12 Lunch:
Nov. 14 Continue working on exterior until finished Nov. 19 Lunch:
Thanksgiving week
Nov. 28 Begin insulating interior Dec. 03 Lunch:
Dec. 05 Insulate and begin hanging sheetrock Dec. 10 Lunch:
Dec. 12 Sheetrock
Dec. 19 Finish hanging sheetrock
Christmas week
New Years week
Jan. 02 Begin taping sheetrock Jan. 07 Lunch:
Jan. 09 Taping and texturing Jan. 14 Lunch:
Jan. 16 Taping and texturing Jan. 21 Lunch:
Jan. 23 Prime interior Jan. 28 Lunch:
Jan. 30 Finish priming all interior walls Feb. 04 Lunch:
Feb. 06 Begin interior painting Feb. 11 Lunch:
Feb. 13 Finish interior painting Feb. 18 Lunch:
Feb. 20 Hang doors Lunch: Sub to install interior trim and cabinets, hang doors
Feb. 27 Begin installing interior trim
March 05 Finish all doors and trim Lunch:
March 12 Caulking March 17 Lunch:
March 19 Caulking and clean interior March 24 Lunch:
Spring break
April 02 Install cabinets Lunch:
April 09 Fence building April 14 Lunch: Sub to install floor coverings
April 16 Landscaping and fence building complete April 21
April 23 Misc. work completed
April 30 Clean up Subs to finish
May 07 Final inspection
May 14 House Dedication
To schedule your “build day,” or for more information call 459-3344, or Contact Us